Case Study: Power Distribution Assembly – NSN: 6110-01-558-9427

Artemis received, as a part of a contract with Raytheon, a power distribution assembly from a Light Armored Vehicle LAV-25A1. The condition of this unit was as follows:

  • This power distribution assembly arrived with severe corrosion
  • Most components were unsalvageable
  • Water intrusion and corrosion in all the cabling
  • Required all new components, extensive corrosion treatment: acid wash of internal cavity, and finally primed and painted

Artemis replaced damaged components, executed corrosion control and retested the board for functionality. Circuit cards did not need to be replaced: Artemis technicians cleaned, reapplied conformal coating, and completed final testing.

  • Turn-around time:
  • Received item: 7/25/11
  • Overhauled and Shipped: 10/17/11